Capital Projects / Projects
Updating Actions
As the project progresses, you will need to update action information, such as the actual date started, date completed, person-hours performed, and the action item status. When you are executing a project, you may want to edit the actual costs associated with an action. You can review and edit actual costs using the Management Console Adjust tab.
Access the Management Console from:
- Projects / Plan / Management Console: Plan
- Projects / Procure / Management Console: Procure
For more information on using the Management Console, see the Using the Management Console (Plan/Procure) topic.
To update an action, including actual costs:
- Select the Execute / Management Consoles: Adjust task.
- Select the project
that contains the actions that you want to edit.
The Management Console appears with the Request Change Order tab selected. - Select the Update Actions tab.
- Select the action that you want to edit.
- Edit the Cost - Actual (Capital) and Cost - Actual (Expense) values.
- Edit the following additional fields
as necessary:
Completed By/Date Completed: If the action item is completed, you can add this information for it.
Action Item Status: Update the status to reflect the action's current status. Reports, such as Action Status by Action Type, use the action item status.
Date Started: Enter the actual date the action started.
Document: Click the Check In New Document button next to the Document field to select a document to associate with the action.
Duration- Actual (Days) : This field is calculated from the Date Start, Date Completed, and Days Per Week fields, and is not editable.
Hours - Actual: Enter the number of person-hours spent on the project. For example, if the action's Duration is two days, and two people worked on this action for eight-hour days, then the person-hours for this action is 32 hours. The S-Curve analysis uses person-hours in its calculations for work, so it is important to enter these hours if you are generating S-Curve charts.
Verified by/Date Verified: If verification is part of your process, add this information.
- Click the Save button to save your changes.